Basically negative float is the amount of
time the project is behind, as determined by the total time for the
tasks on the critical path exceeding the time available for the project.
There is only zero or negative float on the critical path; by
definition the critical path doesn't have positive float. Negative
float is something you want to fix.
http://www.projectmanagementquestions.com/2538/when-to-use-a-negative-float